A Steady Pace for the Project |
||||
| 1991 (Nov.) |
Fr. Norbert Wood is approved as the first Norbertine priest to be assigned as chaplain and teacher at Mary Star of the Sea High School. |
|||
|
1994 (June) |
Father Norbert is appointed principal. |
|||
|
1994 (Sept.) |
School enrollment is 256. |
|||
|
1994 (Nov.) |
A school development group is organized to investigate options for gathering resources (assets). |
|
||
|
1995 (Mar.) |
The development group identifies the availability of US Navy land on Taper Ave as an option. |
|||
|
1995 (May) |
Formal application is submitted to the San Pedro Area Reuse Committee (SPARC) for the Taper Ave. site. |
|||
|
1995 (June) |
Full time Norbertine staff grows to five at the High School. |
|||
|
1996 (April) |
LA City Council formally approves the recommendation of SPARC for Mary Star. |
|||
|
1996 (May) |
Formation of a steering committee for the MSHS project begins. |
|||
|
1996 (Sept.) |
MSHS submits a detailed application for the site to the US Dept. of Education. |
|||
|
1997 (Jan.) |
The Capital Campaign begins for Phase I ($7.5M target for 50,000 sq. ft. of buildings). |
|||
|
1997 (Mar.) |
Mary Star is officially notified by the Dept. of Education of the award of land. |
|||
|
1997 (Sept.) |
School enrollment is 390. |
|||
|
1997 (Oct.) |
BOA Architecture is selected to provide the engineering & pre-architectural planning for MSHS. |
|||
|
1998 (Mar.) |
First year of fund raising ends with $4,645,135 in pledges. |
|||
|
1998 (Dec.) |
Mary Star requests LA Archdiocese Building Commission (ABC) approval to take title to the land and do demolition and grading. |
|||
|
1999 (Jan.) |
Written approval of ABC is granted. |
|||
|
1999 (Jan.) |
The deed is recorded. |
|||
|
1999 (Mar.) |
Second year of fundraising ends with $5,448,542 in pledges. |
|||
|
1999 (May) |
First major foundation grant is received for $800,000 requiring double matching by Dec. 2000. |
|||
|
1999 (Sept.) |
Demolition begins on the site. School enrollment is 445. There are six full time Norbertines on staff. |
|||
|
2000 (Jan.) |
The Capital Campaign breaks $7,000,000. |
|||
|
2000 (May) |
The remodel of existing buildings to become the residence for the Norbertine faculty begins. |
|||
|
2000 (June) |
Master site & facility plans with a preliminary budget are available. |
|||
|
2000 (Sept.) |
School enrolls 450 students. There are eight full time Norbertines on staff and ten on campus. |
|||
|
2000 (Sept.) |
Capital Campaign breaks $8,000,000. |
|||
|
2000 (Oct.) |
Application to the City of Los Angeles for an environmental assessment ruling and a conditional use permit (CPU) is submitted. |
|||
|
2001 (April) |
Norbertines moved into their new monastery on the new campus site. |
|||
|
2001 (Aug.) |
Conditional use permit was unanimously granted by the City of LA review board. |
|||
|
2001 (Dec.) |
$7 million loan from Archdiocese approved. |
|||
2004 (Nov.) |
Groundbreaking |
|||
2005 (Aug.) |
School building construction begins. |
|||
2007 (Sept.) |
Dedication Ceremony led by Cardinal Roger Mahoney. |
|||
2007 (Oct.) |
Classes begin at the new campus. |
|||
|
[Home]
[Administration]
[Admissions]
[Academics]
[Activities]
[Athletics]
[Alumni] [Milestones] [Master Plan] [Deed Transfer] [Demolition] [Design Concept] [Faculty Housing] [CUP]
Mary Star of
the Sea High School E-mail: mshsinfo@marystarhigh.com© 1999 - 2001 SanPedro.comAll Rights Reserved |
||||